This question can be answered without any computation.
As the 80% of work is done in the last 6 days( 20% of 30 days). Then the work done in the last 14 days must be more than 80% i.e. 4/5 (For the possible answer the numerator must be greater than half of the denimenator) and there are two possible options A (13x/15 ) and D (2x/3 ) Clearly D is just 66.67% and the obvious choice is answer choice A.
Or, if we want to kill some time and do the tedious job of computing, we can do the same as follows
...
As the 80% of work is done in the last 6 days( 20% of 30 days). Then the work done in the last 14 days must be more than 80% i.e. 4/5 (For the possible answer the numerator must be greater than half of the denimenator) and there are two possible options A (13x/15 ) and D (2x/3 ) Clearly D is just 66.67% and the obvious choice is answer choice A.
Or, if we want to kill some time and do the tedious job of computing, we can do the same as follows
...