hi, could you plz explain how 2/5, 4/11 and 3/10 came?
Its Option B here.
John can complete the work in 15 hours so the amount of work completed in hour= 1/15
Bill can complete the work in 6 hours, so the amount of work complete in one hour= 1/6
Add above two,
1/15+ 1/6 = 7/30.
Now Test the answer choices,
Option 1: 7/30+ 1/ X = 2/5 => X= 6 hours.
Option 2: 7/30 + 1/X= 4/11 (x=Around 7. 5 ish...)
Option 3: 7/30 + 1/x = 3/10 (X is 15)
OPTION 4 and 5 will be definitely greater than 15.
...
shriramvelamuri wrote:
Its Option B here.
John can complete the work in 15 hours so the amount of work completed in hour= 1/15
Bill can complete the work in 6 hours, so the amount of work complete in one hour= 1/6
Add above two,
1/15+ 1/6 = 7/30.
Now Test the answer choices,
Option 1: 7/30+ 1/ X = 2/5 => X= 6 hours.
Option 2: 7/30 + 1/X= 4/11 (x=Around 7. 5 ish...)
Option 3: 7/30 + 1/x = 3/10 (X is 15)
OPTION 4 and 5 will be definitely greater than 15.
...