Bunuel wrote:
If it takes Jacob x hours to complete a project and it takes Mike y hours to complete the same project, how many hours will it take them to complete the project if they are working together?
A. xy/(x+y)
B. (x+y)/(xy)
C. x+y
D. xy
E. x–y
Jacob's 1 hour's work = 1/x
Mike's 1 hour's work=1/y
Jacob and Mike's 1 hour's work=1/x + 1/y
= (x+y)/xy
Now (x+y)/xy is done in 1 hour
So, the entire work will be done by = xy/(x+y), which is option A.
...